Gypsum Board

Project Execution Plan

  • Material Sample Submission
  • Sample Selection & Approvals
  • Material Sample Testing
  • Design revision
  • Final approval
  • Revision to integrate with main project programme.
  • Final approval
  • Survey & levelling
  • Inspection and acceptance of backing structure
  • Site measurement and production if cutting sheet
  • Material handling
  • Pre- installation works
  • Actual starting dates of fixing : 10 days after arrival of material
  • Completion of installation by 6 months

Work Procedures

Read More about our work procedures